Real plans, created with PathHub AI

Project plan examples for internal initiatives

Project plan examples for internal initiatives cover CRM rollouts, office moves, compliance, technology, and operational changes, with complete plans created using PathHub AI. Each plan includes phases, tasks, schedules, budgets, risks, stakeholders, compliance obligations, owners, effort, and dependencies. Plans can be opened in the app or created from a description.

  • 13 example plans
  • Phases, budget, risks
  • Open without sign-up
11 Weeks

Project plan: CRM rollout

A CRM rollout rarely fails because of the software. It fails on data quality, adoption in sales and unclear ownership.

6 Phases 28 Tasks €66,000
View plan
11 Weeks

Project plan: Office move

An office move touches almost every department: IT, facilities, purchasing, HR and the works council.

6 Phases 30 Tasks €98,000
View plan
34 Weeks

Project plan: ISO 27001 certification

ISO 27001 certification is not an IT project but a management system: scope, risk assessment, Annex A controls, internal audit and management review have to fit together.

10 Phases 67 Tasks €216,350
View plan
30 Weeks

Project plan: NIS2 implementation

With NIS2, risk management, incident reporting and supply chain security become mandatory for far more companies, and management is personally liable.

10 Phases 83 Tasks €378,000
View plan
15 Weeks

Project plan: Time-tracking rollout

Many companies are introducing working-time recording: in Germany a Federal Labour Court ruling made it mandatory.

6 Phases 36 Tasks €39,950
View plan
28 Weeks

Project plan: ERP implementation

An ERP implementation changes purchasing, production, warehouse and accounting at the same time. It rarely fails because of the software, but on master data, processes and key users without time.

10 Phases 67 Tasks €577,600
View plan
52 Weeks

Project plan: SAP S/4HANA implementation

Moving from SAP ECC to S/4HANA is more than a technical upgrade: custom code has to be cleaned up, processes reviewed, test cycles planned and users trained.

14 Phases 121 Tasks €3,696,000
View plan
20 Weeks

Project plan: Website relaunch

A website relaunch involves marketing, sales, HR and IT, and without a clean SEO migration it puts years of search visibility at risk.

10 Phases 61 Tasks €230,500
View plan
16 Weeks

Project plan: E-invoicing rollout

Since 2025, companies in Germany must be able to receive e-invoices; the obligation to send them follows step by step in 2027 and 2028.

7 Phases 39 Tasks €58,500
View plan
12 Weeks

Project plan: Whistleblowing system

Under the German Whistleblower Protection Act, companies with 50 or more employees need an internal reporting office with fixed deadlines for acknowledgement and feedback.

6 Phases 29 Tasks €42,650
View plan
16 Weeks

Project plan: Recruiting and onboarding

Filling many positions at once takes more than job ads: employer brand, selection process, works council approval, written terms of employment and an onboarding that keeps new people.

7 Phases 42 Tasks €97,600
View plan
14 Weeks

Project plan: Access control and video surveillance

Access control and video surveillance process employee data and can monitor behaviour.

9 Phases 49 Tasks €194,500
View plan
26 Weeks

Project plan: Cloud migration

A cloud migration is more than moving servers: data processing agreements, third-country transfers, NIS2 supply chain security and a disaster recovery concept must be in place before the first application moves.

10 Phases 54 Tasks €817,500
View plan

Your initiative

Describe it in a few sentences: the complete plan is ready in minutes.

Create a plan

What every plan includes

Not a template to fill in, but a complete plan: created from a description.

Phases and tasks

With owners, effort and predecessors.

  • Tick off, move and add tasks
  • Status per phase: pending, in progress, review, completed, blocked, delayed
  • Adjust owners, effort and dates per task
  • Critical tasks at a glance
See it in the example plan

Schedule

Gantt with parallel phases and dependencies.

  • Drag phases to move them, drag the edges to change duration
  • See parallel phases and dependencies
  • Milestones right in the schedule
  • Zoom between detail and full view
See it in the example plan

Budget

Line items with quantity and unit price, later actual costs.

  • Edit line items with quantity and unit price
  • Record costs: planned, committed, billed
  • Actual and committed costs are calculated automatically
  • Export as PDF (from Team) or Excel (Business)
See it in the example plan

Risks

Rated, with concrete countermeasures.

  • Rated by impact: high, medium, low
  • Countermeasure with owner and timing
  • Add your own risks or regenerate them with instructions
  • Risk matrix in the AI tools
See it in the example plan

Stakeholders

Who to involve, why and from when.

  • Role, reason and timing of involvement
  • Stakeholder map in the AI tools
  • Invite your team with owner, editor and viewer roles (from Team)
  • Read-only link for management and stakeholders: no account needed
See it in the example plan

Compliance

Obligations such as GDPR, works council and industry rules.

  • Obligations from 93 curated rules for EU, DE, AT and CH
  • Marked as mandatory or important, with owner and deadline
  • Add your own requirements
  • Regenerate with instructions, e.g. “focus on IT security”
See it in the example plan

Your initiative isn't listed?

Describe it in a few sentences: PathHub builds the complete plan in minutes. No sign-up.

Create a plan →