What is Earned Value Analysis?

Earned Value Analysis (EVA) -- also known as Earned Value Management (EVM) or Earned Value Analysis -- is the most powerful method in project controlling. It simultaneously answers the three crucial questions of every project: Are we on budget? Are we on schedule? How much have we actually accomplished?

Unlike a simple planned vs. actual cost comparison, EVA integrates the project scope, costs, and schedule into a single view. It doesn't just show that you spent 60,000 euros, but also whether you created 60,000 euros worth of value for it -- or only 40,000 euros.

Why EVA is the Standard

Earned Value Analysis was developed in the 1960s by the US Department of Defense and is now a core part of the PMBOK Guide (PMI), DIN 69901, and ISO 21508. It is used especially in large projects, public tenders, and regulated industries -- but is also useful for medium-sized projects with budgets from around 50,000 euros.

Automatic in PathHub

PathHub tracks planned and actual costs per budget line and task progress: the figures you need for an earned value view. Try it without signing up →

The Three Basic Metrics: PV, EV, AC

The entire Earned Value Analysis is built on just three basic metrics. If you understand these, you understand EVA:

PV

Planned Value

The planned value: How much budget should have been spent according to the plan by the status date? Also called "Budgeted Cost of Work Scheduled" (BCWS).

EV

Earned Value

The earned value: How much value (measured by budget) was actually completed? Also called "Budgeted Cost of Work Performed" (BCWP).

AC

Actual Cost

The actual costs: How much money was actually spent by the status date? Also called "Actual Cost of Work Performed" (ACWP).

Mnemonic: PV = What was planned? EV = What was accomplished? AC = What did it cost? Comparing these three values immediately shows if your project is on track.

A crucial point: Earned Value (EV) measures progress in euros, not in percent. If a work package is budgeted at 10,000 euros and is 50% complete, the EV is 5,000 euros -- regardless of how much was actually spent.

Earned Value Analysis: S-Curves Visualized

Comparison of Planned Value (PV), Earned Value (EV), and Actual Cost (AC) for project control.

Earned Value Management $0 $25k $50k $75k $100k W0 W3 W6 W9 W12 W15 Time (Weeks) Cost Today SV (negative) = behind schedule CV (negative) = over budget PV (Planned Value) EV (Earned Value) AC (Actual Cost)

EVM chart: The project is behind schedule (SV negative) and over budget (CV negative). PathHub AI calculates these KPIs automatically.

Calculating Variances: CV and SV

The cost and schedule variances can be calculated from the three basic metrics:

Cost Variance CV = EV - AC Positive = under budget | Negative = over budget
Schedule Variance SV = EV - PV Positive = ahead of schedule | Negative = behind schedule

The Cost Variance (CV) compares what was accomplished (EV) with what it cost (AC). If you created 50,000 euros worth of value but spent 60,000 euros, the CV is -10,000 euros -- you are 10,000 euros over budget.

The Schedule Variance (SV) compares what was accomplished (EV) with what should have been accomplished according to the plan (PV). If you created 50,000 euros worth of value, but according to the plan you should have accomplished 70,000 euros, the SV is -20,000 euros -- you are behind schedule.

Performance Indices: CPI and SPI

While CV and SV show absolute variances, CPI and SPI express efficiency as a ratio -- ideal for comparing projects of different sizes:

Cost Performance Index CPI = EV / AC = 1.0: on budget | > 1.0: under budget | < 1.0: over budget
Schedule Performance Index SPI = EV / PV = 1.0: on schedule | > 1.0: ahead of schedule | < 1.0: behind schedule
Metric Formula Meaning if < 1.0 Meaning if = 1.0 Meaning if > 1.0
CPI EV / AC Over Budget On Budget Under Budget
SPI EV / PV Behind Schedule On Schedule Ahead of Schedule
Practical Rule: CPI below 0.8 is a Warning Signal

Studies show that the CPI hardly improves after the 20% mark of a project. If your CPI is below 0.8 after the first fifth of the project, the budget will very likely be significantly exceeded. The earlier you intervene, the better.

Forecasts: EAC and ETC

The most powerful function of EVA: You can forecast what the project will cost at completion based on the performance to date:

Estimate at Completion (forecasted total cost) EAC = BAC / CPI BAC = Budget at Completion (total budget) | Assumption: current efficiency continues
Estimate to Complete (forecasted remaining cost) ETC = EAC - AC How much budget is still needed for the remainder of the project?
Variance at Completion (forecasted budget variance) VAC = BAC - EAC Positive = finish under budget | Negative = finish over budget

There are different EAC formulas, depending on the assumption about future performance. The formula above (BAC / CPI) assumes that the current cost efficiency will continue -- the most realistic assumption in most cases.

Practical Example: Software Project

A company is developing a new web application. The project has a total budget (BAC) of 200,000 euros and a planned duration of 20 weeks. After 10 weeks (midpoint), an EVA is performed:

Work Package Budget (PV) Completion Earned Value (EV) Actual Cost (AC)
Requirements Analysis 20,000 € 100 % 20,000 € 22,000 €
UI/UX Design 30,000 € 100 % 30,000 € 28,000 €
Backend Development 40,000 € 75 % 30,000 € 38,000 €
Frontend Development 30,000 € 50 % 15,000 € 18,000 €
Testing 10,000 € 20 % 2,000 € 3,000 €
Total after 10 weeks 130,000 € 97,000 € 109,000 €

Calculating the Metrics

Variances CV = 97,000 - 109,000 = -12,000 €
SV = 97,000 - 130,000 = -33,000 € The project is 12,000 euros over budget and 33,000 euros behind schedule.
Performance Indices CPI = 97,000 / 109,000 = 0.89
SPI = 97,000 / 130,000 = 0.75 For every euro spent, only 89 cents of value are generated. Only 75% of the planned work is completed.
Forecasts EAC = 200,000 / 0.89 = 224,719 €
ETC = 224,719 - 109,000 = 115,719 €
VAC = 200,000 - 224,719 = -24,719 € If efficiency remains constant, the project will cost approximately 25,000 euros more than planned.

Interpreting Results: The Four Scenarios

The combination of CPI and SPI results in four possible scenarios. Each requires a different response:

Scenario CPI SPI Meaning Actions
Ideal Project > 1.0 > 1.0 Under budget and ahead of schedule Stay the course, potentially release resources for other projects
Schedule Pressure > 1.0 < 1.0 Under budget, but behind schedule Invest surplus budget in additional resources to catch up
Cost Pressure < 1.0 > 1.0 Over budget, but ahead of schedule Review efficiency, reduce scope, or use cheaper resources
Crisis Project < 1.0 < 1.0 Over budget and behind schedule Immediate escalation, scope reduction, create a recovery plan

Our example project (CPI = 0.89, SPI = 0.75) falls into the "Crisis Project" scenario. The project manager should act immediately: analyze the causes of inefficiency, review the scope (can features be cut?), evaluate additional resources, and inform the stakeholders about the situation.

Prerequisites and Limitations of EVM

Prerequisites for Successful EVM

Limitations of EVM

Practical Tip: The 0/50/100 Method

For work packages whose progress is difficult to estimate, the 0/50/100 method is suitable: a package is either not started (0%), in progress (50%), or completed (100%). This is simpler than an exact percentage and prevents unrealistic "90% complete" estimates that remain at 90% for weeks.

Plan, actuals and progress in one place

PathHub builds the plan with a budget and tracks costs and progress.

Create a plan, no sign-up

Frequently Asked Questions

Earned Value Analysis (EVA) is a project controlling method that integrates cost, schedule, and project scope into a single view. It compares the planned value (Planned Value), the actual value earned (Earned Value), and the actual costs (Actual Cost) to objectively determine whether a project is on time and within budget.
CPI (Cost Performance Index) measures cost efficiency: CPI = EV / AC. A CPI of 1.0 means "on budget", below 1.0 means "over budget", above 1.0 means "under budget". SPI (Schedule Performance Index) measures schedule efficiency: SPI = EV / PV. An SPI of 1.0 means "on schedule", below 1.0 means "behind schedule", above 1.0 means "ahead of schedule".
EVA is particularly suitable for projects with a clearly definable scope, measurable work packages, and a budget over 50,000 euros. It is typically used from the execution phase onwards, when planned and actual values can be compared. It is less suitable for very agile or exploratory projects.
CV (Cost Variance = EV - AC) shows the cost variance in absolute numbers: positive means under budget, negative means over budget. SV (Schedule Variance = EV - PV) shows the schedule variance: positive means ahead of schedule, negative means behind schedule. Both values complement the respective indices CPI and SPI.